Construction progress

TAP is currently moving further into the project construction phase. Every day hundreds of meters of TAP’s Right of Way (ROW) are cleared, strung, welded, lowered into the trenches and backfilled, in line with the project construction steps and schedule.

At the end of the third quarter of 2017, the TAP project was:

58% completed

Disclaimer: the above completeness percentage includes all engineering and procurement scope as well as the progress on the 12 pipeline construction steps onshore, offshore construction and installation, the construction of above ground installations (block valve stations, compressor stations and pipeline receiving terminal) as well as offshore pipeline installation. 

The map below shows progress across three key construction stages along TAP’s route: ROW clearing, pipe welding and backfilling of welded pipes lowered into the trenches.

Disclaimer: Please note that the coloured areas along TAP’s route are representative only. The information is updated on a quarterly basis.