Pipeline construction in Greece

The length of the pipeline in Greece is approximately 550 kilometres. TAP’s longest section, it will start at Kipoi, near the country’s border with Turkey, and finish at its border with Albania, south-west of Ieropigi.

The Greek section will include one compressor station near Kipoi for 10 bcm and an additional one near Serres should TAP’s capacity be upgraded to 20 bcm. There will be 22 block valve stations along the Greek route.

Watch the video illustrating how the pipeline is built in Greece:

Please note that all figures mentioned in the text are estimates and can change as the project develops.